Union Minister for Electric Power U Thaung Han together with government Chief Ministers and officials inspected the Solar+Gas Engine Hybrid power plant project site near Magway township in Magway region. They also inspected land reclamation work, engine foundation work, generators, completion of construction of Construction Power, construction of fence and completion of the construction of the project entrance road.
The 120 megawatts the Solar+Gas Engine Hybrid power plant project is being built on a land area of 490 acres near Thabyaysan village in Magway township of Magway Region. The installed power of the machine is 120 megawatts, and after the completion of the project, the generated power will be connected to the national power system through the 132 KV Magway Main Substation.
Source: Myawady Daily Newspaper (2-4-2023)
- After the completion the 120 megawatts the Solar+Gas Engine Hybrid power plant project, the generated power will be connected to the national power system through the 132 KV Magway Main Substation.